Stage 6: Energization

Stage 6 marks the final stage of the Connection Process. An Energization Checklist/Deficiency List must be completed upon which energization of the transmission facilities can occur. For generators, a commissioning period applies following which a Commissioning Certificate is issued. The TFO provides the final project costs and a true-up occurs so that project close-out can take place.