Alberta Electric System
Operator
Long Term Critical
Transmission Outages > 10 days (Revised 2012-02-02)
The following table
contains the critical transmission maintenance outages submitted as tentative to the AESO.
These outages have not
yet necessarily been approved, but are listed for awareness and coordination
purposes.
An outage has been
considered critical for this table if it affects:
- a 500 kV Line, Breaker, Bus or
Transformation,
- a 240 kV Line, Breaker, Bus or
Transformation,
- the interconnection of the AIES to an
external transmission system, specifically the BC intertie or the
Saskatchewan intertie
- a significant
component of the AIES, is an interconnecting element between transmission
facility owners,
or connects a generating
unit to the AIES
- requires curtailing
generation to facilitate the outage.
Note: Where a
transmission outage requires generation curtailments, the adjustments to
generation will typically
happen in the hour
before the scheduled transmission outage and in the hour after the element is
returned to service.
Owner From To Duration Element Scheduled Activity Affected Intertie*
ENMAX 27-Oct-11 8:00 15-Feb-12 16:00 Continuous ENMAX 31.1 cap bank
(FORCED) forced outage AB-BC
ATCO 16-Nov-11 1:00 29-Feb-12 17:00 Continuous 828s Sulphur Point 507C1
and 507C2 damage (one wafer blow up)
(forced outage)
ENMAX 13-Jan-12 17:01 15-Mar-12 16:00 Continuous 162B240-RB135 (162s
Beddington) moved to replace failed breaker RB135
ATCO 19-Jan-12 17:00 04-Apr-12 17:00 Continuous 856s900BUS1 (no outage) install new 240 kV breakers and associated
equipment
AltaLink 03-Feb-12 8:00 27-Feb-12 16:00 Continuous 1045L (310p - E805s)
Advice for Epcor EPCOR re-stringing
portion of 1045L
EPCOR 03-Feb-12 8:00 28-Feb-12 16:00 Continuous 1045L (805s Jasper - 310p
Sundance) Jasper re-string project
AltaLink 07-Feb-12 17:30 21-Feb-12 17:00 Continuous 928L (17s Benalto-42s
Sarcee) line move AB-BC
ENMAX 10-Feb-12 19:30 12-Feb-12 19:30 C 917L (74s Janet - 5s East
Calgary) install new structure
AltaLink 13-Feb-12 8:00 16-Feb-12 17:00 Continuous 17s8 GOI. Replace 240KV CT
AltaLink 13-Feb-12 8:00 17-Feb-12 17:00 Daily 913L(69s-A732s) Advice
for ATCO Pole replacement and mitigation
maintenance.
ATCO 13-Feb-12 8:00 14-Feb-12 17:00 Continuous 888S DOVER 888S900BS1 CUTTING IN JUMPER "J1" @ 888S
DOVER
900BS1
EPCOR 13-Feb-12 8:00 15-Feb-12 16:00 Continuous 1056 Line 814S Bellamy to
89S Ellerslie SF6 Gas Maintenance (High Moisture)
ATCO 13-Feb-12 8:30 17-Feb-12 17:30 Continuous 9L913 9L913 replace poles
ATCO 14-Feb-12 17:00 01-Mar-12 17:00 Continuous 888S DOVER
888SPORTION900BS1 install new equipment
AltaLink 15-Feb-12 9:00 15-Feb-12 17:00 71s1052 (C2) GOI maintain SF6 240 kV ABB -
HPL capbank
AltaLink 16-Feb-12 9:00 16-Feb-12 17:00 54s45 (C1) GOI C/S & Cap Bank
Maintenance
AltaLink 20-Feb-12 8:00 24-Feb-12 17:00 Daily 913L(69s-A732s) Advice
for ATCO Pole replacement and mitigation
maintenance.
ATCO 20-Feb-12 8:30 24-Feb-12 17:30 Continuous 9L913 9L913 replace poles
AltaLink 21-Feb-12 8:00 24-Feb-12 17:00 Continuous 17s12 GOI. Replace 240KV CT
AltaLink 21-Feb-12 8:00 24-Feb-12 17:00 Continuous 368s35 GOI Replace CTs.
AltaLink 21-Feb-12 11:00 22-Feb-12 17:00 Continuous 370s56 GOI 240kV Breaker Maintenance
AltaLink 23-Feb-12 9:00 23-Feb-12 17:00 59s452 GOI 240kV Breaker Maintenance
AltaLink 27-Feb-12 8:00 02-Mar-12 17:00 Continuous 17s5 GOI. Replace 240KV CT
AltaLink 27-Feb-12 8:00 02-Mar-12 17:00 Continuous 901L (74s-64s-63s) GOI Construction AB-BC
AltaLink 27-Feb-12 8:00 02-Mar-12 17:00 1005L (356s-370s) GOI Construction
AltaLink 27-Feb-12 8:00 29-Feb-12 16:00 Continuous 72s990 (990L) Advice for
ATCO Raise 9L990 for 7L104 construction - ATCO
ATCO 27-Feb-12 8:30 02-Mar-12 17:30 Continuous 9L913 9L913 replace poles
AltaLink 27-Feb-12 9:00 27-Feb-12 14:00 256s C1 GOI Remove Bird Nest
AltaLink 29-Feb-12 9:00 29-Feb-12 17:00 72s652 GOI 240 kV Breaker
Maintenance
ATCO 02-Mar-12 7:00 02-Mar-12 19:00 9L57 9L57 INSTALLING TEMPORARY
BYPASS
ATCO 02-Mar-12 19:00 30-Mar-12 8:00 Continuous 9L57 PART9L57 BUILDING IN/OUT TO NEW
939S LIVOCK
ATCO 05-Mar-12 7:30 09-Mar-12 16:00 Continuous 9L990 9L990 raising line for future
substation
AltaLink 05-Mar-12 8:00 08-Mar-12 17:00 Continuous 1036L (356s-370s) GOI Construction
AltaLink 05-Mar-12 8:00 08-Mar-12 17:00 Continuous 17s7 GOI. Replace 240KV CT
AltaLink 05-Mar-12 8:00 09-Mar-12 17:00 Daily 913L(69s-A732s) Advice
for ATCO pole replacement and mitigation maintenance
ATCO 05-Mar-12 8:00 12-Mar-12 17:00 Continuous 9L961 9L961 required for new
construction at 825s
Whitefish
ATCO 05-Mar-12 8:30 09-Mar-12 17:30 Continuous 9L913 9L913 replace poles
ATCO 11-Mar-12 8:00 13-Mar-12 16:00 Continuous 977S SALT CREEK 9L85 connect to 977s Salt
Creek
AltaLink 12-Mar-12 8:00 15-Mar-12 17:00 Continuous 908L(38s-E52s-89s)GOI. Construction. Thermal upgrade
ATCO 12-Mar-12 8:00 19-Mar-12 17:00 Continuous 825S WHITEFISH 825S904 REQUIRED FOR NEW CONSTRUCTION @
825S WHITEFISH
AltaLink 13-Mar-12 8:00 13-Mar-12 17:00 912L (63s-A766s) GOI YTG relay replacement
ATCO 14-Mar-12 6:30 18-Mar-12 18:00 Continuous 9L55 9L55 install new towers for
future tap-off
AltaLink 15-Mar-12 8:00 15-Mar-12 17:00 63s (925L) GOI YTG Relay Replacement AB-BC
EPCOR 15-Mar-12 8:00 15-Apr-12 16:00 Continuous 1056 Line 814S Bellamy to
89S Cable maintenance
Ellerslie
AltaLink 16-Mar-12 8:00 19-Mar-12 17:00 Continuous 908L(89s-E816s) GOI Construction. Thermal
upgrade
AltaLink 19-Mar-12 8:00 20-Mar-12 17:00 Continuous 903L(17s300) GOI Replace B and C phases of
17s300 Pts(899 AB-BC
and 901)
ATCO 19-Mar-12 8:00 04-Apr-12 17:00 Continuous 9L22 9L22 REQUIRED FOR NEW
CONSTRUCTION @
825S WHITEFISH
ATCO 19-Mar-12 8:00 18-Jun-12 16:00 Continuous 801s Anderson 801s907 rebuild new bay for 9L33
AltaLink 20-Mar-12 8:00 23-Mar-12 17:00 Continuous 909L (89s-E665s) GOI Construction. Thermal
upgrade
AltaLink 21-Mar-12 8:00 29-Mar-12 17:00 Continuous 913L (69s - 310p) GOI cut in new 338s station
AltaLink 24-Mar-12 8:00 28-Mar-12 17:00 Continuous 909L (320p-E665s) GOI Construction. Thermal
upgrade
ATCO 30-Mar-12 8:00 30-Mar-12 16:00 9L57 9L57 closing jumper J1
EPCOR 15-Apr-12 8:00 15-May-12 16:00 Continuous 1056 Line 814S Bellamy to
89S Ellerslie Cable maintenance
AltaLink 16-Apr-12 11:00 19-Apr-12 17:00 Continuous 19sT10 GOI 19s T10 tapchanger
overhaul
AltaLink 21-Apr-12 8:00 24-Apr-12 17:00 Continuous 42s 240 kV North(T1)
& South(T2) and create an open point AB-BC
906L
AltaLink 01-May-12 8:00 14-May-12 17:00 Continuous 102s SVC GOI & 240kv
west bus replace SVC TX
AltaLink 02-May-12 8:00 03-May-12 17:00 Continuous 163s1352 GOI 240kV Breaker Maintenance
AltaLink 14-May-12 8:00 22-May-12 17:00 Continuous 100L (498s-895s) GOI Line move to accommodate
road widening
near 895s
AltaLink 14-May-12 8:00 14-May-12 17:00 917L (74s-5s) GOI Construction carry over
ATCO 19-May-12 9:00 20-May-12 16:00 Continuous 9L59 9L59 create a temp by-pass for
the Tinchebray
ATCO 20-May-12 8:00 22-May-12 8:00 Continuous 9L950 9L950 Install Tap-off structor
piles
ATCO 01-Jun-12 9:00 08-Jun-12 16:00 Continuous 9L950 9L950 REROUTE 9L950 TO ALLOW
FOR
OAKLAND CROSS-OVER
ATCO 04-Jun-12 8:00 05-Jun-12 16:00 Continuous 801S ANDERSON
801S901T&701T INSTALL RIDER POLES NEAR
901T AND
701T, THIS WILL OPEN-END
7L85
ATCO 19-Jun-12 8:00 03-Aug-12 16:00 Continuous 801S ANDERSON REBUILD OLD 9L933 BAY
FOR 9L97
801SBKRS905&906
ATCO 25-Jun-12 9:00 26-Jun-12 16:00 Continuous 9L59 9L59 CUT-IN NEW TINCHEBRAY
AltaLink 16-Jul-12 8:00 19-Jul-12 17:00 Continuous 172L (83s - 172L944A) Work between str 328
& 951. Structure and
cross arm
ATCO 06-Aug-12 8:00 02-Nov-12 16:00 Continuous 801S ANDERSON 801SBKR903 REBUILD NEW BAY FOR 9L933
ATCO 13-Nov-12 8:00 20-Nov-12 16:00 Continuous 801s Anderson 801s905
& 801s906 connect new 9L97 to bay
ATCO 21-Nov-12 8:00 22-Nov-12 16:00 Continuous 801s Anderson
801S901T&701T remove rider poles
ATCO 01-Apr-13 8:00 30-Jun-13 17:00 Continuous 840s McNeill HVDC control system
upgrade AB-SK
[1] AB-BC & AB-SK: refer to AESO web posting: http://itc.aeso.ca/itc/public/atcQueryInit.do
Also,
[2] AB-BC: refer to
OPP-304 at: http://www.aeso.ca/rulesprocedures/9073.html
[3] AB-SK: typical impact
is ATC = 0
Prepared on: February-02-2012 16:47
This document and the information
contained herein are based upon information and data which by their nature
contain a degree of uncertainty and are subject to change. In addition, this document may contain
information
and data from public sources and/or third parties, which have been
assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator,
operating as the Alberta Electric System
Operator (the “AESO”) makes no warranty, representation or
guarantee, express or implied, with respect to this document or the information
contained herein, including, but not limited to, any warranty, representation
or
guarantee of accuracy, completeness, timeliness, reliability,
availability, absence of computer virus, non-infringement, merchantability or
suitability for any purpose. Under no
circumstances will the AESO, its members,
officers, employees, contractors or agents, or any of their
respective affiliates, be liable for any errors or omissions in, or any losses,
damages or claims whatsoever, whether in contract, tort or otherwise, arising
from use of or
reliance upon, this document or any information contained
herein.
© 2009 Alberta Electric System Operator. All rights reserved.