Alberta Electric System Operator

                             Long Term Critical Transmission Outages > 10 days (Revised 2012-02-02)

    The following table contains the critical transmission maintenance outages submitted as tentative  to the AESO.

    These outages have not yet necessarily been approved, but are listed for awareness and coordination purposes.

    An outage has been considered critical for this table if it affects:

             -  a 500 kV Line, Breaker, Bus or Transformation,

             -  a 240 kV Line, Breaker, Bus or Transformation,

             -  the interconnection of the AIES to an external transmission system, specifically the BC intertie or the

             Saskatchewan intertie

             - a significant component of the AIES, is an interconnecting element between transmission facility owners,

             or connects a generating unit to the AIES

             - requires curtailing generation to facilitate the outage.

    Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically

    happen in the hour before the scheduled transmission outage and in the hour after the element is returned to service.

  Owner                  From                  To              Duration     Element                                   Scheduled Activity  Affected Intertie*

     ENMAX       27-Oct-11  8:00     15-Feb-12     16:00       Continuous      ENMAX 31.1 cap bank (FORCED)        forced outage                   AB-BC

     ATCO        16-Nov-11  1:00     29-Feb-12     17:00       Continuous      828s Sulphur Point 507C1 and 507C2    damage (one wafer blow up)

                                                                                               (forced outage)

     ENMAX       13-Jan-12 17:01     15-Mar-12     16:00       Continuous      162B240-RB135 (162s Beddington)     moved to replace failed breaker RB135

     ATCO         19-Jan-12 17:00     04-Apr-12     17:00       Continuous      856s900BUS1 (no outage)                install new 240 kV breakers and associated

                                                                                                                                               equipment

     AltaLink      03-Feb-12  8:00     27-Feb-12     16:00       Continuous      1045L (310p - E805s) Advice for Epcor EPCOR re-stringing portion of 1045L

     EPCOR       03-Feb-12  8:00     28-Feb-12     16:00       Continuous      1045L (805s Jasper - 310p Sundance) Jasper re-string project

     AltaLink      07-Feb-12 17:30     21-Feb-12     17:00       Continuous      928L (17s Benalto-42s Sarcee)          line move                         AB-BC

     ENMAX       10-Feb-12 19:30     12-Feb-12     19:30                  C      917L (74s Janet - 5s East Calgary)      install new structure

     AltaLink      13-Feb-12  8:00     16-Feb-12     17:00       Continuous      17s8 GOI.                                    Replace 240KV CT

     AltaLink      13-Feb-12  8:00     17-Feb-12     17:00              Daily      913L(69s-A732s) Advice for ATCO     Pole replacement and mitigation

                                                                                                                                               maintenance.

     ATCO        13-Feb-12  8:00     14-Feb-12     17:00       Continuous      888S DOVER 888S900BS1                CUTTING IN JUMPER "J1" @ 888S DOVER

                                                                                                                                               900BS1

     EPCOR       13-Feb-12  8:00     15-Feb-12     16:00       Continuous      1056 Line 814S Bellamy to 89S Ellerslie SF6 Gas Maintenance (High Moisture)

     ATCO        13-Feb-12  8:30     17-Feb-12     17:30       Continuous      9L913 9L913                                replace poles

     ATCO        14-Feb-12 17:00     01-Mar-12     17:00       Continuous      888S DOVER 888SPORTION900BS1     install new equipment

     AltaLink      15-Feb-12  9:00     15-Feb-12     17:00                          71s1052 (C2) GOI                          maintain SF6 240 kV ABB - HPL capbank

     AltaLink      16-Feb-12  9:00     16-Feb-12     17:00                          54s45 (C1) GOI                             C/S & Cap Bank Maintenance

     AltaLink      20-Feb-12  8:00     24-Feb-12     17:00              Daily      913L(69s-A732s) Advice for ATCO     Pole replacement and mitigation

                                                                                                                                               maintenance.

     ATCO        20-Feb-12  8:30     24-Feb-12     17:30       Continuous      9L913 9L913                                replace poles

     AltaLink      21-Feb-12  8:00     24-Feb-12     17:00       Continuous      17s12 GOI.                                   Replace 240KV CT

     AltaLink      21-Feb-12  8:00     24-Feb-12     17:00       Continuous      368s35 GOI                                  Replace CTs.

     AltaLink      21-Feb-12 11:00     22-Feb-12     17:00       Continuous      370s56 GOI                                  240kV Breaker Maintenance

     AltaLink      23-Feb-12  9:00     23-Feb-12     17:00                          59s452 GOI                                  240kV Breaker Maintenance


     AltaLink      27-Feb-12  8:00     02-Mar-12     17:00       Continuous      17s5 GOI.                                    Replace 240KV CT

     AltaLink      27-Feb-12  8:00     02-Mar-12     17:00       Continuous      901L (74s-64s-63s) GOI                   Construction                     AB-BC

     AltaLink      27-Feb-12  8:00     02-Mar-12     17:00                          1005L (356s-370s) GOI                    Construction

     AltaLink      27-Feb-12  8:00     29-Feb-12     16:00       Continuous      72s990 (990L) Advice for ATCO         Raise 9L990 for 7L104 construction - ATCO

     ATCO        27-Feb-12  8:30     02-Mar-12     17:30       Continuous      9L913 9L913                                replace poles

     AltaLink      27-Feb-12  9:00     27-Feb-12     14:00                          256s C1 GOI                                 Remove Bird Nest

     AltaLink      29-Feb-12  9:00     29-Feb-12     17:00                          72s652 GOI                                  240 kV Breaker Maintenance

     ATCO        02-Mar-12  7:00     02-Mar-12     19:00                          9L57 9L57                                   INSTALLING TEMPORARY BYPASS

     ATCO        02-Mar-12 19:00     30-Mar-12       8:00       Continuous      9L57 PART9L57                             BUILDING IN/OUT TO NEW 939S LIVOCK

     ATCO        05-Mar-12  7:30     09-Mar-12     16:00       Continuous      9L990 9L990                                raising line for future substation

     AltaLink      05-Mar-12  8:00     08-Mar-12     17:00       Continuous      1036L (356s-370s) GOI                    Construction

     AltaLink      05-Mar-12  8:00     08-Mar-12     17:00       Continuous      17s7 GOI.                                    Replace 240KV CT

     AltaLink      05-Mar-12  8:00     09-Mar-12     17:00              Daily      913L(69s-A732s) Advice for ATCO     pole replacement and mitigation maintenance

     ATCO        05-Mar-12  8:00     12-Mar-12     17:00       Continuous      9L961 9L961                                required for new construction at 825s

                                                                                                                                               Whitefish

     ATCO        05-Mar-12  8:30     09-Mar-12     17:30       Continuous      9L913 9L913                                replace poles

     ATCO        11-Mar-12  8:00     13-Mar-12     16:00       Continuous      977S SALT CREEK 9L85                   connect to 977s Salt Creek

     AltaLink      12-Mar-12  8:00     15-Mar-12     17:00       Continuous      908L(38s-E52s-89s)GOI.                  Construction. Thermal upgrade

     ATCO        12-Mar-12  8:00     19-Mar-12     17:00       Continuous      825S WHITEFISH 825S904                REQUIRED FOR NEW CONSTRUCTION @

                                                                                                                                               825S WHITEFISH

     AltaLink      13-Mar-12  8:00     13-Mar-12     17:00                          912L (63s-A766s) GOI                     YTG relay replacement

     ATCO        14-Mar-12  6:30     18-Mar-12     18:00       Continuous      9L55 9L55                                   install new towers for future tap-off

     AltaLink      15-Mar-12  8:00     15-Mar-12     17:00                          63s (925L) GOI                              YTG Relay Replacement       AB-BC

     EPCOR       15-Mar-12  8:00     15-Apr-12     16:00       Continuous      1056 Line 814S Bellamy to 89S           Cable maintenance

                                                                                               Ellerslie

     AltaLink      16-Mar-12  8:00     19-Mar-12     17:00       Continuous      908L(89s-E816s) GOI                      Construction. Thermal upgrade

     AltaLink      19-Mar-12  8:00     20-Mar-12     17:00       Continuous      903L(17s300) GOI                          Replace B and C phases of 17s300 Pts(899                AB-BC

                                                                                                                                               and 901)

     ATCO        19-Mar-12  8:00     04-Apr-12     17:00       Continuous      9L22 9L22                                   REQUIRED FOR NEW CONSTRUCTION @

                                                                                                                                               825S WHITEFISH

     ATCO        19-Mar-12  8:00     18-Jun-12     16:00       Continuous      801s Anderson 801s907                  rebuild new bay for 9L33

     AltaLink      20-Mar-12  8:00     23-Mar-12     17:00       Continuous      909L (89s-E665s) GOI                     Construction. Thermal upgrade

     AltaLink      21-Mar-12  8:00     29-Mar-12     17:00       Continuous      913L (69s - 310p) GOI                     cut in new 338s station

     AltaLink      24-Mar-12  8:00     28-Mar-12     17:00       Continuous      909L (320p-E665s) GOI                    Construction. Thermal upgrade

     ATCO        30-Mar-12  8:00     30-Mar-12     16:00                          9L57 9L57                                   closing jumper J1

     EPCOR       15-Apr-12  8:00    15-May-12     16:00       Continuous      1056 Line 814S Bellamy to 89S Ellerslie Cable maintenance

     AltaLink      16-Apr-12 11:00     19-Apr-12     17:00       Continuous      19sT10 GOI                                  19s T10 tapchanger overhaul

     AltaLink      21-Apr-12  8:00     24-Apr-12     17:00       Continuous      42s 240 kV North(T1) & South(T2) and  create an open point           AB-BC

                                                                                                906L

     AltaLink      01-May-12  8:00    14-May-12     17:00       Continuous      102s SVC GOI & 240kv west bus        replace SVC TX

     AltaLink      02-May-12  8:00    03-May-12     17:00       Continuous      163s1352 GOI                               240kV Breaker Maintenance

     AltaLink      14-May-12  8:00    22-May-12     17:00       Continuous      100L (498s-895s) GOI                     Line move to accommodate road widening

                                                                                                                                               near 895s

     AltaLink      14-May-12  8:00    14-May-12     17:00                          917L (74s-5s) GOI                          Construction carry over


     ATCO        19-May-12  9:00    20-May-12     16:00       Continuous      9L59 9L59                                   create a temp by-pass for the Tinchebray

     ATCO        20-May-12  8:00    22-May-12       8:00       Continuous      9L950 9L950                                Install Tap-off structor piles

     ATCO         01-Jun-12  9:00     08-Jun-12     16:00       Continuous      9L950 9L950                                REROUTE 9L950 TO ALLOW FOR

                                                                                                                                               OAKLAND CROSS-OVER

     ATCO         04-Jun-12  8:00     05-Jun-12     16:00       Continuous      801S ANDERSON 801S901T&701T      INSTALL RIDER POLES NEAR 901T AND

                                                                                                                                               701T, THIS WILL OPEN-END 7L85

     ATCO         19-Jun-12  8:00    03-Aug-12     16:00       Continuous      801S ANDERSON                           REBUILD OLD 9L933 BAY FOR  9L97

                                                                                               801SBKRS905&906

     ATCO         25-Jun-12  9:00     26-Jun-12     16:00       Continuous      9L59 9L59                                   CUT-IN NEW TINCHEBRAY

     AltaLink       16-Jul-12  8:00      19-Jul-12     17:00       Continuous      172L (83s - 172L944A)                    Work between str 328 & 951. Structure and

                                                                                                                                               cross arm

     ATCO        06-Aug-12  8:00    02-Nov-12     16:00       Continuous      801S ANDERSON 801SBKR903          REBUILD NEW BAY FOR  9L933

     ATCO        13-Nov-12  8:00    20-Nov-12     16:00       Continuous      801s Anderson 801s905 & 801s906    connect new 9L97 to bay

     ATCO        21-Nov-12  8:00    22-Nov-12     16:00       Continuous      801s Anderson 801S901T&701T         remove rider poles

     ATCO        01-Apr-13  8:00     30-Jun-13     17:00       Continuous      840s McNeill                                 HVDC control system upgrade   AB-SK

       [1] AB-BC & AB-SK: refer to AESO web posting:     http://itc.aeso.ca/itc/public/atcQueryInit.do

       Also,

       [2] AB-BC: refer to OPP-304 at:                       http://www.aeso.ca/rulesprocedures/9073.html

       [3] AB-SK: typical impact is ATC = 0

Prepared on:   February-02-2012 16:47

This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change.  In addition, this document may contain information

and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified.  Accordingly, the Independent System Operator, operating as the Alberta Electric System

Operator (the “AESO”) makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or

guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non-infringement, merchantability or suitability for any purpose.  Under no circumstances will the AESO, its members,

officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or

reliance upon, this document or any information contained herein.   

 

© 2009 Alberta Electric System Operator.  All rights reserved.