Alberta Electric System
Operator
System Co-ordination Plan
2010-07-31 to 2010-08-06
Approved Outages
Date From Time Date To Time Owner Type Element Scheduled Activity Interconnection
From To
20-Jan-10 15:00 10-Sep-10 18:00 ATCO COND GTE 815S GOODFARE Change motor to hand operator Continuous
815S703A and commission
01-Feb-10 13:00 01-Sep-10 13:00 ATCO IO 834S WESLEY Install new switch in bus and add Continuous
CREEK 7L12 (no line temp bypass
oos)
01-Mar-10 8:00 31-Dec-10 16:00 ENMAX Outage 138-1.82L (ENMAX 1 - 138 kV cable replacement C
ENMAX 5) & -1.84L
(ENMA 1 - ENMAX 5)
09-Jul-10 9:00 19-Aug-10 17:00 AltaLink Outage 180L (255s Vulcan - line rebuild Continuous
928s East Stavely)
19-Jul-10 8:00 06-Aug-10 17:00 EPCOR Outage 987S Clover Bar CT changeout and Transformer 1 CONT.
Transformer #1 & retro fit
Trans #3
26-Jul-10 8:00 02-Aug-10 16:00 ATCO Outage 7L85 (803s Bullpound - 705 breaker maintenance Continuous
801s Anderson)
26-Jul-10 9:00 20-Aug-10 17:00 BCH Outage Natal T4 install oil containment Continuous AB-BC
27-Jul-10 10:30 03-Aug-10 17:00 ATCO Outage 810S DOME OIL RECLAMATION Continuous
CUTBANK 810S701T
28-Jul-10 7:30 05-Aug-10 18:30 ATCO RB 7L63 (780S LUBICON setting of “rider poles”
close to Daily
TO 788S HOTCHKISS) 7L63 in preparation of stringing the
R/B new lines (7L106 and
7L131) from
834S Wesley to 905S Meikle
28-Jul-10 8:00 09-Aug-10 8:00 ATCO Outage 828s Sulphur Point foundation installation Continuous
828S700BS2
28-Jul-10 17:00 25-Aug-10 17:00 AltaLink Outage 396s Mobile install, SW project & building/switchgear Continuous
affects 170L (396s replacement. 396s10 to remain
Pincher Creek - 239s open to allow protection coordinatio
Castle River)
30-Jul-10 7:00 09-Aug-10 17:00 EPCOR Outage 930L (37s North Calder isolation for the Anthony Henday cont
- 805s Jasper) FWY construction project
30-Jul-10 8:00 01-Aug-10 17:00 AltaLink Outage 914L (86s Bigstone - install A & B protection Continuous AB-BC
89s Ellerslie)
03-Aug-10 7:00 03-Aug-10 17:00 EPCOR TE 9330R 3600 Mux Routine Maintenance 3600 Mux by D
AltaLink crews
03-Aug-10 7:00 03-Aug-10 17:00 AltaLink IO 9330R 3600 Mux - Info Routine Maintenance 3600 Mux
03-Aug-10 7:00 03-Aug-10 17:00 AltaLink TE 352s (104LN) Recloser Troubleshoot Autoreclosing for
- Relay 104LN
03-Aug-10 8:00 03-Aug-10 12:00 ENMAX Outage 69-13.60L affects duct work & backfill cable D
13.60L (ENMAX 13 -
ENMAX 27) and
13.4TR
03-Aug-10 8:00 12-Aug-10 18:00 AltaLink Outage 3L (42s Sarcee -272s replace 3/0 copper conductor with Continuous
Springbank) 266 partidge and change out
structures
03-Aug-10 8:00 13-Aug-10 16:30 AltaLink Outage 370s734X affects 734L breaker replacement Continuous
(370s North
Lethbridge - 241s
Uplands)
03-Aug-10 8:00 06-Aug-10 17:30 AltaLink RB 931L (28s -132s) R/B Line Maintenance Continuous
03-Aug-10 8:00 06-Aug-10 18:00 AltaLink RB 933L (28s - A801s ) Line Maintenance Continuous
RB
03-Aug-10 8:00 05-Aug-10 17:00 AltaLink Outage 80L (217s North Red Replace structures due to river Daily
Deer - 198s erosion
03-Aug-10 8:00 03-Aug-10 17:00 AltaLink TE 28s Relay Relay Upgrade
03-Aug-10 8:00 03-Aug-10 17:00 AltaLink TE 17s Relay Relay Maintenance
03-Aug-10 8:00 03-Aug-10 17:00 AltaLink Outage 38s T3 GOI AMI installation
03-Aug-10 8:00 05-Aug-10 16:00 ATCO Outage 709s Vegreville 702T & breaker 602 maintenance Continuous
709702T & 6L79 (709s
Vegreville - 711s
Willingdon) open
ended at 709s
03-Aug-10 8:00 05-Aug-10 17:30 ATCO RB 9L59 NONE SWAY BRACE REPLACEMENT Continuous
03-Aug-10 9:00 05-Aug-10 17:00 AltaLink Outage 310P2652 (310p breaker maintenance & repair Continuous
Sundance) grading cap leaks
03-Aug-10 10:00 04-Aug-10 15:00 ATCO Outage 6L02 (757s Battle maintain 604 breaker Continuous
River - 6L02D2)
03-Aug-10 10:30 03-Aug-10 17:00 ATCO Outage 813s Little Smoky partial maintenance on 702
813S702
03-Aug-10 13:00 03-Aug-10 17:00 AltaLink Outage 28sR1, affects reactor doble testing
(28s West Brooks)
04-Aug-10 7:00 05-Aug-10 17:00 AltaLink Outage 910L (89s Ellerslie - Protection install B for FCSI Continuous AB-BC
63s Red Deer)
04-Aug-10 7:00 04-Aug-10 17:00 AltaLink IO 320p 3600 Mux - Info Routine Maintenance 3600 Mux
04-Aug-10 7:00 04-Aug-10 17:00 AltaLink IO 9320R 3600 Mux - Info Routine Maintenance 3600 Mux
04-Aug-10 8:00 04-Aug-10 17:00 AltaLink Outage 28s52 (28s West Breaker Maintenance
Brooks)
04-Aug-10 8:00 07-Aug-10 17:00 AltaLink Outage 172L (370s North Lower 172L & underbuild in Continuous
Lethbridge - 172L1236) preparation for 967/968L stringing
04-Aug-10 8:00 04-Aug-10 17:00 AltaLink TE 415s Relay Relay Testing
04-Aug-10 8:00 04-Aug-10 17:00 AltaLink Outage 38s T2 (38s East AMI installation
Edmonton)
04-Aug-10 8:00 04-Aug-10 17:00 ATCO Outage 813s703 (813s Little Partial Maintenance on 703
Smoky)
04-Aug-10 13:00 04-Aug-10 16:00 AltaLink Outage 56L (20s Ghost -245s Switch Maintenance
Seebe)
05-Aug-10 7:00 05-Aug-10 17:00 AltaLink IO 9320P 3600 Mux - Info Routine Maintenance 3600 Mux
05-Aug-10 7:00 05-Aug-10 17:00 AltaLink IO 9310P 3600 Mux - Info Routine Maintenance 3600 Mux
05-Aug-10 7:00 05-Aug-10 17:00 AltaLink IO 9310R 3600 Mux - Info Routine Maintenance 3600 Mux
05-Aug-10 8:00 05-Aug-10 17:00 AltaLink Outage 945s551W (945s breaker maintenance
Sunshine Village)
05-Aug-10 9:00 05-Aug-10 17:00 AltaLink Outage 368s35 (35s Burdett breaker maintenance
Cap Bank)
05-Aug-10 9:00 05-Aug-10 15:00 ATCO Outage 775S 604C, affects 604C Replace conductors
cap bank (775s
Sullivan Lake)
05-Aug-10 9:00 05-Aug-10 12:00 ATCO RB 7L07 (790 Poplar Hill - install marker cones on overhead
815s Goodfare) wire
05-Aug-10 10:00 05-Aug-10 16:00 ATCO Outage 813s Little Smoky partial maintenance on 701
813s701
05-Aug-10 10:00 05-Aug-10 16:00 ATCO Outage 7L67 (824S Fieldgate - replace support stack on pole 3
743S Sarah Lake)
Prepared on: July-28-2010 16:35 Approved Outages Page 3 of 3
This document and the information
contained herein are based upon information and data which by their nature
contain a degree of uncertainty and are subject to change. In
addition, this document may contain information and data from
public sources and/or third parties, which have been assumed to be accurate and
complete and have not been
verified. Accordingly, the
Independent System Operator, operating as the Alberta Electric System Operator
(the “AESO”) makes no warranty, representation or guarantee,
express or implied, with respect to this document or the
information contained herein, including, but not limited to, any warranty,
representation or guarantee of accuracy,
completeness, timeliness, reliability, availability, absence of
computer virus, non-infringement, merchantability or suitability for any
purpose. Under no circumstances will the
AESO, its members, officers, employees, contractors or agents, or
any of their respective affiliates, be liable for any errors or omissions in,
or any losses, damages or claims
whatsoever, whether in contract, tort or otherwise, arising from
use of or reliance upon, this document or any information contained
herein.
© 2009 Alberta Electric System Operator. All rights reserved.