Tariff Effective Jan. 1, 2006
2006 Tariff
The following rates and terms and conditions of service were approved by the Alberta Energy and Utilities Board (EUB) in Order U2005-464 effective January 1, 2006, with amendments to certain rates in Order U2006-307 effective January 1, 2006.
-
Rates Effective January 1, 2006
[Posted: December 22, 2005] -
Terms and Conditions Effective January 1, 2006
[Posted: December 22, 2005]
2006 Changes to System Access Service Rates and Terms and Conditions
The AESO's 2006 tariff included significant changes from previous tariffs in compliance with the Government of Alberta's Transmission Regulation (A.R. 174/2004). Major changes include:
- Load customers directly pay all costs of the transmission system except for losses.
- Generator customers pay only the cost of losses (and Regulated Generating Unit Connection Costs).
- Generator customers pay a system contribution of $10,000-$50,000/MW for new interconnections after January 1, 2006, refundable over ten years with satisfactory performance.
The 2006 tariff were approved by the Alberta Energy and Utilities Board (EUB) in Decisions 2005-096, 2005-131, and 2005-132, and in Orders U2005-464 and U2006-307. Major changes include introduction of new charges and new billing determinants, changes to ratchet levels, approval of a Balancing Pool Consumer Allocation refund rider, changes to investment levels, and changes to application fees. See the Highlights summary below for a summary of the changes, or the tariff documents for the approved rates and terms and conditions of service.
-
2006-01-31 AESO 2006 Tariff - Highlights
[Posted: January 31, 2006]