Stage 5: Construction
In Stage 5 construction of transmission facilities required for the connection commences. The Customer and AESO are required to sign the corresponding System Access Service Agreement 6 weeks prior to energization. Data required to authorize energization of the facilities is required in order to complete Gate 5.