Key Activities & Requirements to pass Gate 2
Key Activities:- Connection studies completed
- Customer completes or accepts Connection Proposal
- AESO completes Stage 2 Construction Contribution Decision (Stage 2 CCD)
- Customer submits Stage 2 Project Data Update Package (includes specific machine data for dynamic studies)
- Customer enters into an agreement for Stage 3 and 4 costs
- Upon completion of Gate 2, the project is added to the Connection Queue.
Gate 2 Completion Requirements:
- AESO accepts Connection Proposal (or Customer accepts if AESO completes)
- Stage 2 Project Data Update Package is complete
- Customer has met security requirements for Stage 3 and 4 costs related to preparation of the NID and/or FA