Transmission System Needs Identification Documents
|
Alberta’s transmission system, sometimes referred to as the Alberta Interconnected Electric System (AIES) or “grid,” is planned and operated by the AESO. The AIES is comprised of the high-voltage lines, towers and equipment (generally 69 kV and above) that transmit electricity from electric generators to lower voltage systems that distribute it to cities, towns, rural areas and large industrial customers. It is the AESO's role to maintain safe, reliable and economic operation of the AIES. The AESO’s planning responsibility includes identifying needed transmission development and recommending preferred options to meet these needs. The AESO must apply to the Alberta Utilities Commission (AUC) for approval of transmission system needs identified in a Needs Identification Document (NID). Stakeholders have the opportunity to provide comments to the AESO on the need identified prior to the AESO filing the NID. Once the AUC approves the NID, the AESO will direct assign the construction of the project to the a transmission facilities owner (TFO). The TFO will then file an application with the AUC for approval of the transmission facilities that will satisfy the transmission system development need identified by the AESO. The table below includes the AESO’s current transmission system NIDs. The AESO Planning Areas are defined in the AESO Planning area map. Needs Identification Documents will be removed from the website 30 days following the TFOs Facility Application approval by the AUC. If you require a NID that no longer appears on our website please contact Stakeholder Relations at stakeholder.relations@aeso.ca or 1-888-866-2959. |
Northeast |
|
Needs Identification Document |
Planning Area |
Need Description |
Status of Needs Identification Document |
| Algar Area System Development | Fort McMurray Area Area 25 |
Need for transmission system development to meet increased demand | Approved by the AUC on April 18, 2013 |
| Beartrap 940S Substation Connection | Cold Lake Area Area 28 |
Need for transmission system development to meet increased demand | Filed with the AUC on October 19, 2012 |
| Christina Lake Area Transmission System Development | Fort McMurray Area Area 25 |
Need for transmission system development to meet increased demand | Approved by the AUC on April 24, 2012 |
| Edwards Lake 189S Substation | Fort McMurray Area Area 25 |
Need for transmission system development to meet increased demand | Participant Involvement Program underway |
| Egg Lake 2021S Substation | Fort McMurray Area Area 25 |
Need for transmission system development to meet increased demand | Participant Involvement Program underway |
| Engstrom to Kinosis Transmission Line and Kinosis 856S Substation Upgrade |
Fort McMurray Area |
Need for transmission system development to meet increased demand | Participant Involvement Program underway |
| Grist Lake 190S Substation | Fort McMurray Area Area 25 |
Need for transmission system development to meet increased demand | Participant Involvement Program underway |
| Kettle River 2049S and Bohn 931S Substations |
Fort McMurray Area |
Need for transmission system development to meet increased demand |
Approved by the AUC on March 25, 2013 |
| Mackay River Project Connection |
Fort McMurray Area |
Need for transmission system development to connect an industrial customer | Participant Involvement Program underway |
| Medley River 2003S Substation | Cold Lake Area Area 28 |
Need for transmission system development to meet increased demand | Participant Involvement Program underway |
| Northwest of Fort McMurray 240kV Transmission System Development |
Fort McMurray Area |
Need for transmission system development to meet increased demand |
Approved by the AUC on June 18, 2012 |
| Saleski 901S Substation |
Fort McMurray Area |
Need for transmission system development to meet increased demand | Approved by the AUC on April 4, 2013 |
| Underwood 183S Substation | Fort McMurray Area Area 25 |
Need for transmission system development to meet increased demand | Filed with the AUC on March 19, 2013 |
| Willow Lake 2009S Substation | Fort McMurray Area Area 25 |
Need for transmission system development to meet increased demand | Participant Involvement Program underway |
Northwest
|
Needs Identification Document |
Planning Area |
Need Description |
Status of Needs Identification Document |
| Buchanan Creek 927S Substation | Peace River Area Area 19 |
Need for transmission system development to meet increased demand |
Approved by the AUC on April 19, 2013 |
| Ksituan River Substation Upgrade | Grande Prairie Area 20 |
Need for transmission system development to meet increased demand |
Filed with the AUC on March 18, 2013 |
|
High Level Area |
Need for transmission system development to meet increased demand |
Participant Involvement Program underway | |
| Swan Hills Synfuel Facility Connection | Swan Hills Area Area 26 |
Need for transmission system development to connect new generation |
Participant Involvement Program underway |
| Whitecourt Industrial 364S Substation Upgrade | Swan Hills Area Area 26 |
Need for transmission system development to meet increased demand |
Filed with the AUC on October 3, 2012 |
Edmonton
|
Needs Identification Document |
Planning Area |
Need Description |
Status of Needs Identification Document |
| Bernese 293S Substation | Edmonton Area Area 60 |
Need for transmission system development to meet increased demand |
Participant Involvement Program underway |
| Cherhill 338S Substation Upgrade | Wabamun Area Area 40 |
Need for transmission system development to maintain system reliability | Filed with the AUC on September 13, 2012 |
| Knightsbridge 216S Substation | Edmonton Area Area 60 |
Need for transmission system development to increase reliability | Filed with the AUC on March 15, 2013 |
| Onoway 352S Substation Upgrade | Wabamun Area Area 40 |
Need for transmission system development to meet increased demand |
Approved by the AUC on March 12, 2013 |
| South and West of Edmonton Transmission Development | Edmonton, Wabamun, Wetaskiwin Areas Areas 60, 40, 31 |
Need for transmission system development to meet increased demand |
Filed with the AUC on December 14, 2012 |
Central
|
Needs Identification Document |
Planning Area |
Need Description |
Status of Needs Identification Document |
| Buck Lake 454S Substation Upgrade | Drayton Valley Area Area 30 |
Need for transmission system development to meet increased demand |
Filed with the AUC on October 12, 2012 |
| Bull Creek Wind Energy Connection | Provost Area Area 37 |
Need for transmission system development to connect new generation | Participant Involvement Program underway |
|
Cold Lake, Vegreville, Lloydminster, Wainwright, Provost, Alliance/Battle River Areas Area 28, 56, 13 32, 37, 36 |
Need for transmission system development to meet increased demand and connect new generation |
Amendment approved by the AUC on March 27, 2013 | |
| Harmattan Energy Centre Connection |
Didsbury Area |
Need for transmission system development to connect new generation | Participant Involvement Program underway |
| BluEarth Hand Hills Wind Energy Connection | Hanna Area Area 42 |
Need for transmission system development to connect new generation |
Filed with the AUC on March 8, 2013 |
| Nilrem 574S Substation Upgrade | Wainright Area Area 32 |
Need for transmission system development to meet increased demand |
Participant Involvement Program underway |
| Red Deer Region Transmission Development | Didsbury, Red Deer, Wetaskiwin Areas Areas 39, 35, 31 |
Need for transmission system development to meet increased demand | Approved by the AUC on April 10, 2012 |
| Red Deer Timberland Substation | Red Deer Area Area 35 |
Need for transmission system development to meet increased demand | Participant Involvement Program underway |
| Suncor Hand Hills Wind Energy Connection | Hanna Area Area 42 |
Need for transmission system development to connect new generation | Participant Involvement Program underway |
| Sundre 575S Substation Modification | Caroline Area Area 38 |
Need for transmission system development to meet increased demand |
Approved by the AUC on April 19, 2013 |
| Vista Coal 270S Substation | Hinton/ Edson Area Area 29 |
Need for transmission system development to meet increased demand | Participant Involvement Program underway |
South
|
Needs Identification Document |
Planning Area |
Need Description |
Status of Needs Identification Document |
| Big Rock Transmission Development | High River Area Area 46 |
Need for transmission system development to meet increased demand |
Participant Involvement Program underway |
| Cope Creek Substation Development | Seebe Area Area 44 |
Need for transmission system development to meet increased demand |
Approved by the AUC on December 21, 2012 |
|
Calgary Area |
Need for transmission system development to connect new generation |
Filed with the AUC on August 30, 2012 | |
| ENMAX No. 21 Substation Modification | Calgary Area Area 6 |
Need for transmission system development to meet increased demand |
Approved by the AUC on April 2, 2013 |
|
Calgary Area |
Need for transmission system development to connect new generation |
Approved by the AUC on November 1, 2012 | |
|
Fort Macleod Area |
Need for transmission system development to meet increased demand |
Approved by the AUC on May 10, 2013 | |
|
Calgary, Strathmore/Blackie, High River Areas |
Need for transmission system development to meet increased demand, increased generation, and maintain system reliability |
Filed with the AUC on July 5, 2012 | |
| Highway 785 Wind Farm Connection |
Fort Macleod Area |
Need for transmission system development to connect new generation |
Participant Involvement Program underway |
| Hull 257S Substation | Vauxhall Area Area 52 |
Need for transmission system development to meet increased demand |
Filed with the AUC on November 6, 2012 |
| Lethbridge Chinook NW Substation | Lethbridge Area Area 54 |
Need for transmission system development to meet increased demand |
Participant Involvement Program underway |
| McLaughlin Wind Power Facility Connection |
Fort Macleod Area |
Need for transmission system development to connect new generation |
Participant Involvement Program underway |
| New Dayton Wind Energy Connection | Glenwood Area Area 55 |
Need for transmission system development to connect new generation |
Participant Involvement Program underway |
|
Fort Macleod Area |
Need for transmission system development to meet increased demand |
Amendment approved by the AUC on March 27, 2013 | |
|
Medicine Hat Area |
Need for transmission system development to connect new generation |
Filed with the AUC on June 19, 2012 | |
| Riverview Wind Farm Connection |
Fort Macleod Area |
Need for transmission system development to connect new generation |
Participant Involvement Program underway |
|
Strathmore Blackie, Brooks, Empress, High River, |
Need for transmission system development to reinforce southern Alberta’s transmission system |
Approved by the AUC on September 8, 2009 | |
| Tilley 498S Substation Upgrade | Brooks Area Area 47 |
Need for transmission system development to meet increased demand | Approved by the AUC on April 5, 2013 |
| Waiparous 639S Substation | Seebe Area Area 44 |
Need for transmission system development to meet increased demand | Participant Involvement Program underway |
|
Fort Macleod Area |
Need for transmission system development to connect new generation |
Filed with the AUC on November 19, 2012 |
The AESO welcomes feedback about its consultation process to successfully engage stakeholders in transmission development and planning activities. If you have any suggestions, questions or concerns please contact Stakeholder Relations at stakeholder.relations@aeso.ca or 1-888-866-2959.