    Calgary Energy Centre Peaking Plant Connection

    FortisAlberta Inc. (FortisAlberta) has applied to the Alberta Electric System Operator (AESO) for transmission system access to reliably serve industrial load growth in the Sherwood Park area. FortisAlberta’s request can be met by the following solution:

    • Build the Anthony Henday substation with two 138/25 kV transformers, two 138 kV circuit breakers, and associated equipment.
    • Build one 138 kV transmission line to connect the Anthony Henday substation to the transmission system.

    Need overview

    Notification of regulatory filing advertisement

    Needs Identification Document

    Calgary Energy Centre Peaking Plant Connection NID [Posted:January 24, 2017]

    Appendix A - Connection Assessment
    Appendix B - TFO Capital Cost Estimates
    Appendix C - AESO PIP
    Appendix D - Info Re Rule 007 Sec 6.2.1 - NID 23(3)
    Appendix E - AESO Transmission Planning Criteria - Basis and Assumptions

    Contact us

    We appreciate your views, both on the need for transmission system development and proposed transmission plans. If you have any questions or comments, please contact us directly.

    AESO Stakeholder Relations
    stakeholder.relations@aeso.ca
    1-888-866-2959

    Latest updates

    • Jan. 4, 2017 Calgary Energy Centre Peaking Plant Connection - Notice of NID Filing
    • Oct. 27, 2016 Calgary Energy Centre Peaking Plant Connection – Need for Transmission System Development in the Calgary area