    East Crossfield 64S Substation Upgrade

    FortisAlberta Inc. (FortisAlberta) has applied to the AESO for transmission system access to reliably serve growing demand for electricity in the Town of Crossfield area. FortisAlberta’s request can be met by the following solution:

    • Upgrade the existing East Crossfield 64S substation, including adding a 138/25 kilovolt (kV) transformer and two 138 kV circuit breakers.
    • Add or modify associated equipment as required for the above transmission developments.

    Need overview

    Latest updates

    • Nov. 20, 2017 Need for Transmission Development in the Town of Crossfield Area