    Freer 2043S Substation (2382)

    ATCO Electric Ltd. (ATCO) has applied to the AESO for transmission system access to serve a new demand for electricity in the Fort McMurray area. ATCO’s request can be met by the following solution:

    • Add the Freer 2043S substation, including one 144 kilovolt (kV) circuit breaker and one 144/25 kV transformer.
    • Add one 144 kV transmission line to connect the Freer 2043S substation to the existing 144 kV transmission line 7L121 in a T-tap configuration.
    • Add or modify associated equipment as required for the above transmission developments.

    Need overview

    Latest updates

    • Dec. 2, 2021 Need Overview: Freer 2043S Substation