    Hand Hills Wind Project Connection

    BluEarth Renewables Hand Hills Wind Limited Partnership, on behalf of its general partner, BER Hand Hills Wind GP Inc. (BER Hand Hills LP) has applied to the AESO for transmission system access to connect its approved Hand Hills Wind Project (Facility) in the Delia area. BER Hand Hills LP's request can be met by the following solution:

    • Add one 144 kilovolt (kV) transmission line to connect the Facility to the existing 144 kV transmission line 7L128 in a T-tap configuration.
    • Add or modify associated equipment as required for the above transmission developments.

    Need Overview

    Latest updates

    • Jun. 8, 2021 Need Overview: Hand Hills Wind Project Connection