    Horizon Mining 838S Substation Modification

    Canadian Natural Resources Limited (CNRL)has applied to the AESO for transmission system access to relocate an existing 240 kV transmission linein the Fort MacKay area. CNRL’s request can be met by the following solution:

    • Modify the existing Horizon Mining 838S substation including adding six 240 kV circuit breakers.
    • Add two segments of 240 kV transmission line (9L32 and 9L66) between the Horizon Mining 838S substation and the existing 240 kV transmission lines 9L32 and 9L66.
    • Remove a segment of the existing 240 kV transmission lines 9L32 and 9L66 between the existing Joslyn 849S substation and the connection point with the new segments of 9L32 and 9L66.
    • Add or modify associated equipment as required for the above transmission developments.

    Need Overview

    Latest updates

    • Nov. 10, 2020 Need Overview: Horizon Mining 838S Substation Modification