    Ksituan River 754S Substation Upgrade

    ATCO Electric Ltd. (ATCO) has applied to the Alberta Electric System Operator (AESO) for transmission system access to serve new and growing demand for electricity in the Spirit River area. ATCO’s request can be met by the following solution:

    • Upgrade the existing Ksituan River 754S substation, including adding a 144/25 kilovolt (kV) transformer and a 144 kV circuit breaker.
    • Add or modify associated equipment as required for the above transmission developments.

    Need overview

    Need to upgrade the Ksituan River 754S Substation in the Spirit River Area [Posted: January 24, 2017]

    Notification of regulatory filing advertisement

    Notice of Filing for the Ksituan River 754S Substation Upgrade [Posted: May 3, 2018]

     

    Needs Identification Document

    Ksituan River 754S Capacity Upgrade Needs Identification Document [Posted: May 18, 2018] 

    Appendix A - Connection Assessment
    Appendix B - TFO Capital Cost Estimate
    Appendix C - AESO Participant Involvement Program
    Appendix D - Commission Rule 007, Section 6.2.1 NID15(2)
    Appendix E - DFO Distribution Deficiency Report
    Appendix F - AESO Transmission Planning Criteria - Basis and Assumptions

    Latest updates

    • May. 18, 2018 AESO NID Filed: Ksituan River 754S Capacity Upgrade
    • May. 3, 2018 Notice of Filing for the Ksituan River 754S Substation Upgrade