    Mount Allan 115S Substation Upgrade

    FortisAlberta Inc. (FortisAlberta) has applied to the AESO for transmission system access to reliably serve growing demand for electricity in the Kananaskis Village area. FortisAlberta’s request can be met by the following solution:

    • Upgrade the existing Mount Allan 115S substation, including replacing one existing 138/25 kilovolt (kV) transformer with a 138/25 kV transformer of higher capacity and adding two 138 kV circuit breakers.
    • Add or modify associated equipment as required for the above transmission developments.

    Need overview

    Need for the Mount Allan 115S Substation Upgrade in the Kananaskis Village Area [Posted July 10, 2018]

    Latest updates

    • Jul. 10, 2018 Need for Transmission Development in the Kananaskis Village area