    Okotoks 678S Substation Upgrade and High River 65S Substation Modification

    FortisAlberta Inc. (Fortis) has applied to the Alberta Electric System Operator for transmission system access to improve reliability and to serve growing demand for electricity in the Okotoks and High River areas. Fortis’ request can be met by the following solution:

    • Upgrading the Okotoks 678S substation including adding a 138/25 kV transformer, adding three 138 kV breakers and associated equipment; and
    • Modifying the High River 65S substation including adding two 25 kV breakers and associated equipment.

    Need overview

    Need for the 678S and 65S Substation Upgrades in the Okotoks and High River Areas [Posted: April 6, 2016]

    Notification of regulatory filing advertisement

    Notification of Regulatory Filing [Posted: June 27, 2016]

    Needs Identification Document

    Okotoks 678S Substation Upgrade and High River 65S Substation Modification NID [Posted: July 28, 2016]

    Contact us

    We appreciate your views, both on the need for transmission system development and proposed transmission plans. If you have any questions or comments, please contact us directly.

    AESO Stakeholder Relations
    stakeholder.relations@aeso.ca
    1-888-866-2959

    Latest updates

    • Aug. 2, 2016 Okotoks 678S Substation Upgrade and High River 65S Substation Modification – Needs Identification Document