    Plamondon 353S Substation Upgrade

    FortisAlberta Inc. has applied to the Alberta Electric System Operator for transmission system access. FortisAlberta’s request can be met by the following solution:

    • Adding one 138/25 kV 25/33/42 MVA LTC transformer at the Plamondon 353S Substation; and

    • Adding a 138 kV circuit breaker.

    Need overview

    Need for the Plamondon 353S Substation Capacity Increase in the Hamlet of Plamondon Area [Posted: October 7, 2015]

    Notification of regulatory filing advertisement

    Notification of Regulatory Filing [Posted: February 22, 2016]

    Needs Identification Document

    Plamondon 353S Substation Upgrade NID [Posted: March 23, 2016]