    Turbo Balzac 391S Substation Modification and Chestermere 419S Substation

    FortisAlberta Inc. (FortisAlberta) has applied to the Alberta Electric System Operator (AESO) for transmission system access to reliably supply growing demand for electricity in the Chestermere and Balzac areas. FortisAlberta’s request can be met by the following solution:

    • Construct the Chestermere 419S substation with two 138 kV transformers, three 138 kV circuit breakers, and associated equipment; 
    • Add two 138 kV transmission lines to connect the Chestermere 419S substation to the transmission system; and
    • Modify the Turbo Balzac 391S substation by adding a 25 kV circuit breaker and associated equipment.

    Need overview

    Need for developments in the Chestermere and Balzac Areas [Posted: September 21, 2015]

    Notification of regulatory filing advertisement

    Notification of Regulatory Filing [Posted: August 16, 2016]

    Need Identification Document

    Turbo Balzac 391S Substation Modification and Chestermere 419S Substation NID [Posted: September 9, 2016]

    Contact us

    We appreciate your views, both on the need for transmission system development and proposed transmission plans. If you have any questions or comments, please contact us directly.

    AESO Stakeholder Relations
    stakeholder.relations@aeso.ca
    1-888-866-2959

    Latest updates

    • Sep. 13, 2016 Turbo Balzac 391S Substation Modification and Chestermere 419S Substation – Needs Identification Document
    • Aug. 16, 2016 Transmission developments in the Chestermere and Balzac Areas – Notice of NID filing