New Asset Wheatland Wind (WHE1) Notice
Please note that the effective date of Asset WHE1 has been postponed to Aug. 3, 2022. The previous notification listed an effective date of July 29, 2022.
Wheatland Wind Project LP is connecting a 120 MW wind generator effective Aug. 3, 2022. For information purposes, this new capacity will be reflected on the Current Supply & Demand page effective Aug. 3, 2022.
Please note that the date listed on this notice is the date a new asset will be added to the market. However, many generation units may initially undergo commissioning and testing activities, or incorporation in phases as applicable, and there may be a period of time before the new generation will output its full MW capability on to the grid.