    840 McNeill Converter Tests (AB-SK Intertie)

    ATCO Electric will be performing tests of the McNeill converter station on June 28, 2017 that will affect the import (SK to AB) and export (AB to SK) flows on the Alberta - Saskatchewan intertie.  The expected testing plan is given below.  Please note that energy flows during the testing periods may be variable and change unexpectedly and the volumes given are meant to represent an expected range. 

    June 28, 2017 (10:00 to 11:00): 80 MW AB to SK

    June 28, 2017 (11:00 to 12:00): 80 MW SK to AB

    During the test & trial run period, the AB-SK intertie ATC will be posted as zero for both import and export.

    Should you have any questions, please contact Eric Viray, Manager - Operations Coordination, at ph: 403-705-5209.