    Winnifred Wind Power Project Connection

    Enerfin Energy Company of Canada Inc.(Enerfin) has applied to the AESO for transmission system access to connect its proposed Winnifred Wind Power Project (Facility) in the Whitla area. Enerfin’s request can be met by the following solution:

    • Add one 138 kilovolt (kV) transmission line to connect the Facility to the existing 138 kV transmission line 879L in a T-tap configuration.
    • Add or modify associated equipment as required for the above transmission developments.

    Need Overview

    Need for the Winnifred Wind Power Project Connection in the Whitla area [Posted: Oct. 31, 2019]

    Latest updates

    • Oct. 31, 2019 Need Overview: Winnifred Wind Power Project Connection