    Sweetgrass Solar with Storage Project Connection (2619)

    Neoen Renewables Canada Inc. (Neoen) has applied to the AESO for transmission system access to connect its proposed Sweetgrass Solar with Storage Project (Facility) in the Granum area. Neoen’s request can be met by the following solution:

    • Add a substation, to be designated as Willow Creek 1132S, including three 240 kilovolt (kV) circuit breakers.
    • Connect the proposed Willow Creek 1132S substation to the existing 240 kV transmission line 1038L using an in-and-out configuration.
    • Add one 240 kV transmission line to connect the Facility to the Willow Creek 1132S substation. 
    • Add or modify associated equipment as required for the above transmission developments.

    Need Overview

    Latest updates

    • Jan. 29, 2025 Need Overview: Sweetgrass Solar with Storage Project Connection