Behind the Fence (BTF) Process
This page is intended to provide an overview of the key deliverables and roles and responsibilities for a typical project as it follows the BTF Process. The key deliverables and roles and responsibilities described below may be modified based on the scope and complexity of the project.
For a high-level summary of the Behind the Fence Process, see the Quick Reference Guide:
- Behind the Fence Quick Reference Guide [Posted: Dec. 8, 2022]
-
Acronym Reference
AUC
Alberta Utilities Commission
CCD
Construction Contribution Decision
CEII
Critical Energy Infrastructure Information
DFO
Distribution Facility Owner
DTS
Demand Transmission Service
ETS
Energy Trading System
GFO
Generation Facility Owner
GUOC
Generating Unit Owner’s Contribution
ISD
In-Service Date
MC
Maximum Capability
MP
Market Participant
NID
Needs Identification Document
P&L
Permit & License
PDUP
Project Data Update Package
SAS
System Access Service
SASR
System Access Service Request
SLD
Single Line Diagram
STS
Supply Transmission Service
TFO
Transmission Facility Owner
Stage 0: Application
Target Timeline: 2 weeks
Stage 0 is the initiation stage of the Connection, Behind the Fence, and Contract Processes. In this stage, the market participant identifies a request for a new project by submitting a SASR to the AESO. The SASR is reviewed by the AESO for completeness and the project is initiated. The SASR is reviewed for completeness and the AESO may reach out to the market participant to clarify project information or to discuss project complexity. Upon completion of the review, the project is initiated.
- Required Deliverables
-
Roles and Responsibilities
MARKET PARTICIPANT
- Submits SASR
- Activates account in the CEII Request Portal
AESO
- Reviews SASR
- Assigns project name and number and AESO Project Manager
- After completing all Gate 0 requirements, the AESO issues a letter acknowledging Gate 0 completion to the market participant
-
Additional Information
- For a list of initial steps to consider prior to submitting a SASR to the AESO, see the “Initiating a project” section on the Connecting to the grid page
- Read the SASR Guide for guidance while completing the SASR
- Review ID #2018-018T for further information about the AESO Connection Process
- Read the Principles for External Engagement
- Sign up for the AESO Stakeholder Newsletter for AESO updates in the footer of this webpage
Stage 1: Scope
Target Timeline: 8 weeks
Stage 1 is the scoping stage of the project. This stage includes a project kick-off meeting which begins discussions regarding the Project Plan and Study Scope. The responsibilities and involvement of the AESO, TFO, GFO, market participant, and study consultant are determined for the project.
-
Required Deliverables
- Project Plan
- Study Scope*
- Stage 1 PDUP
-
Roles and Responsibilities
AESO
- Completes Study Scope
- Reviews Project Plan
- Reviews PDUP
- After completing all Gate 1 requirements, the AESO issues a letter acknowledging Gate 1 completion to the market participant
MARKET PARTICIPANT
- Submits Stage 1 PDUP
- Reviews Project Plan and Study Scope
GFO
- Reviews Project Plan and Study Scope
TFO
- Reviews Project Plan and Study Scope
INTEGRATED PM
- Initiates project kick-off meeting
- Completes Project Plan
- Coordinates meetings and takes meeting minutes
- Coordinates deliverables between AESO, market participant, and TFO
-
Additional Information
- The market participant is responsible for performing the necessary studies for the project and is responsible for all project costs
- The study consultant and TFO should attend the kick-off meeting
- Refer to the Project Data Update Package – Instruction Manual (PDUP-IM) for information about the content of the PDUP
- Contact customer.connections@aeso.ca if you would like an example of a Study Scope
Stage 2: Assessment
Target Timeline: 14 weeks
In Stage 2, engineering studies are completed to assess the impact of the project on the grid. The study results are reviewed by the AESO.
-
Required Deliverables
- Engineering Study Results (ESR)*
- SLDs
- Proposal to Proceed
- Stage 2 PDUP
-
Roles and Responsibilities
MARKET PARTICIPANT
- Activates account in the Customer Connections SharePoint Online (SPO) Site and retrieves CEII from the site
- Submits Engineering Study Results and SLDs
- Submits Stage 2 PDUP
AESO
- Uploads CEII to the Customer Connections SPO Site
- Reviews Engineering Study Results and SLDs
- Reviews PDUP
- Issues Proposal to Proceed
- After completing all Gate 2 requirements, the AESO issues a letter acknowledging Gate 2 completion to the market participant
INTEGRATED PM
- Coordinates meetings and takes meeting minutes
- Coordinates deliverables between AESO, market participant, and TFO
-
Additional Information
- See the Connection Study Requirements for more information about how to perform the engineering studies
- Ensure the study consultant communicates with the AESO's Study Engineer prior to starting any work and at any time when issues are identified during the study
- See the Single Line Diagram (SLD) Guideline for information about the content of the SLDs.
- Refer to the Project Data Update Package – Instruction Manual (PDUP-IM) for information about the content of the PDUP
- Set up early meetings with the TFO to understand any costs associated with the project scope
- Market participants have the option to put a project on hold near the end of Stage 2. Please click here to view ID #2018-018T which contains more information.
Stage 3/4: Technical and Contract
Target Timeline: 26 weeks
In Stage 3/4, the AESO issues the Functional Specification for the project and generators are granted power plant approval from the AUC. The market participant and the AESO sign the SAS Agreement.
-
Required Deliverables
- Functional Specification
- Direction Letter*
- Cost Estimate*
- Stage 3/4 CCD*
- SAS Agreement*
- GUOC Notice (generators only)
- Construction Contribution payment or refund*
- GUOC payment (generators only)
- Power Plant Approval (generators only)
-
Roles and Responsibilities
AESO
- Issues Functional Specification and Direction Letter
- Reviews Cost Estimate
- Issues Stage 3/4 CCD
- Issues GUOC Notice
- Executes the SAS Agreement
- After completing all Gate 3/4 requirements, the AESO issues a letter acknowledging Gate 3/4 completion to the market participant
MARKET PARTICIPANT
- Reviews Functional Specification
- Executes the SAS Agreement
- Makes construction contribution payment or receives construction contribution refund
GFO
- Reviews Functional Specification
- Submits GUOC payment
- Confirms Power Plant Approval received
TFO
- Reviews Functional Specification
- Submits Cost Estimate
AUC
- Reviews Power Plant Application and, if approved, provides Power Plant Approval
INTEGRATED PM
- Coordinates meetings and takes meeting minutes
- Coordinate deliverables between AESO, market participant, and TFO
-
Additional Information
- A Project Schedule Alignment is completed and signed by all parties near the beginning of Stage 3
- See Section 504.5 of the ISO rules, Service Proposals and Cost Estimating and the related ID #2015-002R for more information
- To estimate the GUOC amount, refer to the GUOC Estimation Calculator
Stage 5: Construction
Target Timeline: Not applicable
In Stage 5, any equipment or facility modifications occur, including the connection of a generator to the distribution system, and all parties prepare for energization.
-
Required Deliverables
- 100 Day Energization Package which includes the Stage 5 PDUP and Financial Security for SAS Agreements
- 30 Day Energization Package
- ETS setup (generators only)
-
Roles and Responsibilities
AESO
- Reviews items outlined in the Energization Package Requirements
- Reviews application and sets up the GFO and the asset in ETS
- After completing all Gate 5 requirements, the AESO issues a letter acknowledging Gate 5 completion to the market participant
MARKET PARTICIPANT
- Submits required items in the 100 Day Energization Package
- Submits required items in the 30 Day Energization Package
GFO
- Submits required items in the 100 Day Energization Package
- Submits required items in the 30 Day Energization Package
- Submits application to be set up in ETS
TFO
- Submits required items in the 100 Day Energization Package
- Submits required items in the 30 Day Energization Package
INTEGRATED PM
- Coordinates meetings and takes meeting minutes
- Coordinates deliverables between AESO, market participant, and TFO
-
Additional Information
- The Energization Package Requirements provides a detailed list of deliverables and timelines required for energization of the project
- A consolidated Stage 5 PDUP must be submitted by either the market participant, GFO, or TFO. Refer to the Project Data Update Package – Instruction Manual (PDUP-IM) for information about the content of the PDUP.
- A Project Schedule Alignment is completed and signed by all parties near the beginning of Stage 5
- See the Joining the energy market page for more information about how to apply to be set up in ETS
- The market participant may be required to provide financial security to the AESO in this stage. See Section 103.3 of the ISO rules, Financial Security Requirements for more information.
Stage 6: Close Out
Target Timeline: Not applicable
Stage 6 marks the ISD of the project and the final stage of the BTF Process. For generation projects, commissioning of the generator takes place prior to the commercial operation date of the facility.
-
Required Deliverables
- Energization Authorization Letter
- Post-Energization Package
- Commissioning Certificate (generators only)
- Model Validation Report (transmission-connected generators only)
- Final Cost Report*
- Stage 6 CCD*
-
Roles and Responsibilities
AESO
- Issues Energization Authorization Letter
- Reviews items outlined in the Energization Package Requirements
- Issues Commissioning Certificate
- Reviews Model Validation Report
- Reviews Final Cost Report
- Issues Stage 6 CCD
- After completing all Gate 6 requirements, the AESO issues a letter acknowledging Gate 6 completion and closure of the project to the market participant
MARKET PARTICIPANT
- Submits required items in the Post-Energization Package
GFO
- Submits required items in the Post-Energization Package
- Requests Commissioning Certificate
- Submits Model Validation Report
TFO
- Submits Final Cost Report
INTEGRATED PM
- Coordinates meetings and takes meeting minutes
- Coordinates deliverables between AESO, market participant, and TFO
-
Additional Information
- The Energization Package Requirements provides a detailed list of deliverables and timelines required after energization of the project has occurred
- To request the Commissioning Certificate, use the form here
- See Section 504.5 of the ISO rules, Service Proposals and Cost Estimating and the related ID #2015-002R for more information about the Final Cost Report
- For generators, refer to Section 503.19, 503.20 and 505.3 of the ISO rules, for details about commissioning, testing, and the model validation report
* May not be required depending on the scope and complexity of the project