Prairie Lights Power Project Connection (2843)
Prairie Lights Power GP Inc. (PLP) has applied to the AESO for transmission system access to connect its approved Prairie Lights Power Project (Facility) in the Grande Prairie area. PLP’s request can be met by the following solution:
- Add one substation, to be designated as Smoky River 2092S, including five 144 kilovolt (kV) circuit breakers.
- Connect the proposed Smoky River 2092S substation to the existing transmission lines 7L45 and 7L46 using a double in-and-out configuration.
- Add one 144 kV transmission line to connect the Facility to the Smoky River 2092S substation.
- Add or modify associated equipment as required for the above transmission developments.
Need Overview
- Prairie Lights Power Project Connection [Posted: Sep 15, 2026]
Latest updates
- Need Overview: Prairie Lights Power Project Connection